Faisal Town Phase 1 is one of the most sought-after locations for real estate development in Islamabad, offering high-quality infrastructure and modern amenities. Today, we bring you an exclusive update on the construction progress of House 579, situated on Street 12, Block A, an 8 Marla (30×60) plot. This project is being managed by Gondal Group of Marketing, ensuring a smooth and professional construction experience.

Day-by-Day Construction Updates

Construction foundation digging
Day 1: Digging the Foundation

Construction began with the foundation excavation process. The digging phase is crucial to ensure a solid base for the house structure. Expert engineers supervised the work to ensure precision and stability.

Boring for Water

The next phase involved boring for water on-site. This ensures a consistent water supply, which is essential during the construction process and for future household needs.

gravel foundation work at faisal town islamabad
Day 5: Concrete Foundation Work

On other day , concrete pouring was completed for the foundation. This step ensures that the structure will have the strength and durability needed to support the entire building.

steel work
Day 7: Brickwork at the Foundation Level

Brickwork started for the foundation structure, creating a robust and level base. The bricklaying was completed in just three days by a skilled team of workers.

concrete foundation
Day 9: Plinth Level Shuttering and Steel Fixing

After completing the brickwork, the focus shifted to the Plinth level. Shuttering was set up, and steel fixtures were installed, including lower steel reinforcements. This phase was followed by concrete mixing and pouring to secure the structure.

Plinth Beam Concreting

Laborers worked on plinth beam concreting, ensuring a strong beam structure. Proper watering was done to ensure the durability and curing of the concrete.

deshattering of beam level
De-shuttering and Ground Floor Preparation

The plinth beam de-shuttering was completed, and soil removed from the foundation during earlier stages was refilled within the plot premises. Brickwork for the ground floor began shortly after.

refiling of the soil
Watering the Plinth Beam

To maintain the concrete’s strength and prevent cracks, proper watering of the plainit beam was conducted. This step is vital to ensure the long-term durability of the house structure.